Gorgeous Aerial shot!

Check out this aerial view of the temple site!  Glorious!
 
Here are some construction progress details from Elder Holbrook:
 
Work at the Hartford Connecticut Temple construction site is moving along.  The majority of the steel is erected, with the exception of the spire, and the iron workers are busy welding the steel components.
The concrete floor of the mechanical mezzanine, located above the main floor of the temple, was recently poured, and the installation of underground plumbing lines and electrical conduits is underway so the main floor slab can be poured.
 
 